Requirements overview
All created requirements can be found under the tab ‘ Requirements’ > ‘Items’.

Each requirement item shows:
the title of the requirement;
the circle with the number of tasks and progress on completion;
priority (if set);
labels (if any);
due tasks (if any);
test coverage;
test execution progress and results of the linked test cases.

All requirements are divided into two groups: ‘Open’ and ‘Done’. This distribution allows you to focus on those requirements that are not completed yet, and check what has been finished already by applying the filter 'Done' A requirement is considered as ‘Done’ once all tasks inside are marked as completed. Filters When the sheer volume of the requirements gets out of hand, filtering options can help you drill down to see the items you need or check what requirements is not finished yet. You can filter the requirements by:
priority;
labels;
an author.
open/done

Besides, you can filter the requirements by clicking on the priority label or tag on the item itself, and all requirements will be shown on the list. Ordering By default, all requirements are sorted by the date created: from recent to oldest. You can easily change it.
Click on the sorting icon.
Choose the option from the dropdown. When you apply an option, all items are sorted in descending order. If you want them to be shown in ascending order, click on the chosen option once again.

When you apply an option, all items are sorted in descending order. If you want them to be shown in ascending order, click on the chosen option once again.